EDG Architecture + Engineering
58 West 40th St, 5th Fl. New York, NY, 10018
Sign up
2015
OVERVIEW
At Metropolitan Tower, an 80-story residential building on West 57th Street, EDG investigated persistent roof leaks and replaced the topping slab and waterproofing.
The roof is a concrete flat slab with a topping slab that carries a window-washing raceway. Its hot-applied bitumen membrane had reached the end of its service life and was leaking throughout.
APPROACH
The building's height and the topping slab made the membrane difficult to assess, so EDG probed the roof to find the source of the leaks.
Probes revealed an improper pitch in the existing roof deck that was causing leaks at the perimeter. With the cause confirmed, EDG evaluated waterproofing systems and selected the membrane best suited to the topping slab condition.
IMPACT
The new topping slab and waterproofing membrane stopped the leaks that had spread across the roof of the 80-story tower.
EDG coordinated closely with building management, the waterproofing manufacturer, a window-washing rig consultant and the contractor, ensuring the new roof works seamlessly with the building's façade maintenance system.